Paul Esajian, star of A&E®'s hit TV show "Flip This House," is one of the nation's premier real estate investors, building his own company, CT Homes LLC, into a leading multimillion dollar business. Paul has managed more than 300 projects throughout the country. Paul specializes in rehab and contacting systems for successful real estate investors. At any given time, Paul has managed more than 25 development projects with five teams of over 35 contractors in nine different cities and three different states.


Watch Paul on TV!

As seen on A&E®'s
"Flip This House"

Woosley - New Haven, CT


Before and After - Woosley
Exterior — Before
Before and After - Woosley
Exterior — After
Before and After - Rehab Prices

Purchase Price = $65,000

Sale Price = $165,000

Profit after Expenses = $53,100

Restoration Cost After Repairs = $42,000

Description

Two family home, 1700 sq/ft, with 4 bedrooms, and 2 bathrooms. The house was built in 1900. The property had been vacant for about 6 months and had been vandalized numerous times. The house is in a working class neighborhood in a strong rental community. Before and After

Rehab Overview

Property was in need of major renovations. Exterior work included window repair, painting and rebuilding of the existing front porch. Interior work included 2 new kitchens with tile floors and new appliances, 2 new brand bathrooms, all new plumbing and heating systems and electrical updates. New carpet on all floors.

Contractor Overview

Multiple contractors were needed to complete this project. A licensed general contractor was hired for the windows, flooring, kitchen, bathroom, painting and all carpentry. A licensed plumber was hired for all new rough plumbing and finishing. A licensed electrician was hired for all the wiring.

Roof

  1. Inspect entire roof and repair as needed

Exterior - General

  1. Prep & paint entire exterior including front and rear decks (3 tone - body, trim and accent, see attached color scheme)
  2. Rebuild damaged on front deck, install new railing and spindles
  3. Repair all exterior doors were needed, replace all hardware and paint accent color
  4. Install new house numbers, mailboxes and doorbells
  5. Repair all windows were needed
  6. Power wash entire foundation and leave stone color

Landscaping

  1. Cut down all weeds - front and back
  2. Mulch flower beds
  3. Install new white picket fence
Search for listings now!

Interior — General

  1.  Paint scheme: Navajo eggshell walls, semi-gloss white trim & doors, flat white ceilings, white closets, white doors
    • Purchase all paint from Pratt & Lambert
    Color Name Product Code
    Navajo Eggshell Gold Eggshell Navajo Wall (33-32) Z8291
    Ceiling White Gold Flat Super 1-Coat White Z8100
    Trim White Gold Semi-Gloss Super 1-Coat White Z8300
  2. Paint all rooms in house with above color scheme
  3. Remove all trash and debris from all floors
  4. Repair all interior doors as needed (all doors must open and close properly and lock)
  5. Replace all plugs and switches, new light fixtures (brushed nickel trim), were needed

First (1st) floor apartment

  1. Prep and paint rooms (see color scheme above)
  2. Replace switches and outlets as needed, including GFI outlets near kitchen and bathroom sinks
  3. Install new carpet in bedrooms and living rooms
  4. Repair sheetrock as needed in all rooms

Kitchens

  1. Prep walls and paint
  2. Install new Oak cabinets (Lowes Item #141960) and dark laminate countertop (Lowes Item #201881) w/ 7" deep sink (Lowes item #7575)
  3. Install new white appliances (Frig., stove and hood - see attached sheet for item numbers)
  4. New flooring (12" beige ceramic tile) (Lowes Item #188333)
  5. Replace light fixtures (dome with brushed nickel finish) (Lowes item #63853)
Before and After - Woosley
Kitchen — Before
Before and After - Woosley
Kitchen — After

Bathroom

  1. Demo existing bathroom and replace main drain stack
  2. Install new GFI outlet were needed
  3. Move tub location against back wall
  4. Install new 3 piece tub
  5. Move toilet location - (see attached diagram)
  6. Replace sink base, sink top and faucet (lowes item #103612). Install new medicine cabinet
  7. Install new flooring (12" beige ceramic tile - same as kitchen) (Lowes Item #188333)
Before and After - Woosley
Bathroom — Before
Before and After - Woosley
Bathroom — After

Bedrooms

  1. Prep and paint according to color scheme - see above
  2. Repair doors as needed
  3. Replace all light fixtures as needed(Lowes item #63853)
  4. Carpet all floors
Before and After - Woosley
Bedroom — Before
Before and After - Woosley
Bedroom — After
Before and After

Second (2nd) floor apartment

  1. Same scope of work as first floor

Third (3rd) floor apartment

  1. Remove all debris, patch all walls and paint all rooms
  2. Replace all lighting as needed (Lowes item #63853)
  3. Install new berber carpet
  4. Repair doors as needed
Before and After - Woosley
Top floor — Before
Before and After - Woosley
Top floor — After

Basement

  1. Remove all trash and debris
  2. Repair all doors including Bilco doors
  3. Spray entire basement (Kilzs or like product)
  4. Repair lighting as needed
  5. Repair washer and dryer hook up
  6. Service both furnaces
  7. Repair stairs as needed and paint
Search for listings now!

Electrical

  1. Upgrade existing panels as needed to run house
  2. Install 3 new services outside (1 for 1st floor, 1 for 2nd floor and 1 house meter)
  3. Add battery powered smoke/co2 detectors for each floor were needed
  4. Make sure all rooms have overhead lights with switch (no pull chains)
  5. Replace outlets and switches were needed
  6. Replace overhead fan/light in 2 bathrooms.
  7. Make sure we have GFI in bathroom and kitchen were needed
  8. Make sure we have power for hood above stove
  9. Make sure exterior lights work properly
  10. Make sure we have power to boilers
  11. Complete all finish electrical and supply fixtures were needed (brass finish)
  12. Replace electric baseboard heat on 3rd floor
Before and After - Woosley
Electric Box — Before
Before and After - Woosley
Electric Box — After
Before and After - Woosley
Water Heater — Before
Before and After - Woosley
Water Heater — After

FINAL COST BREAKDOWN

  1. Carpenter – $31,500.00
    • Painting Interior/Exterior
    • Rebuild front deck
    • (2) Kitchens (cabinets, countertops - material and labor)
    • Flooring - all carpet and ceramic tile
    • Including all finish work - material and labor
  2. Electrical – $3,200.00
    • Install (3) new panel boxes, light fixtures and smoke/CO2 detectors to code (material and labor)
  3. Plumbing & Heating – $4,500.00
    • Repair all baseboard heat
    • Install all new rough plumbing and complete all finish work, including fixtures
    • Install (2) new hot water heaters
    • Coordinate all inspections, including all material and labor
  4. Permits – $800.00

Total Repair Cost = $42,000.00

Before and After