Paul Esajian, star of A&E®'s hit TV show "Flip This House," is one of the nation's premier real estate investors, building his own company, CT Homes LLC, into a leading multimillion dollar business. Paul has managed more than 300 projects throughout the country. Paul specializes in rehab and contacting systems for successful real estate investors. At any given time, Paul has managed more than 25 development projects with five teams of over 35 contractors in nine different cities and three different states.


Watch Paul on TV!

As seen on A&E®'s
"Flip This House"

Shultas Project - Hartford, CT


Before and After - Shultas
Exterior — Before
Before and After - Shultas
Exterior — After
Before and After - Rehab Prices

Purchase Price = $153,000

Sale Price = $278,000

Profit after Expenses = $47,020

Restoration Cost After Repairs = $68,000

Description

Three family home, 3936 sq/ft with 9 bedrooms and 3 baths. House built in 1910 on .18 ac lot in a quite working class neighborhood near downtown Hartford.
Before and After

Rehab Overview

Property was in need of extensive interior and minor exterior renovations.  All new vinyl replacement windows, new front porch, white picket fence and paint completed the exterior. The rear deck needed minor repairs and paint as well. Three new kitchens, 3 new bathroom, 3 new heating systems and all new flooring and paint throughout. Brand new plumbing and heating was installed on all 3 floors as well as all new electric service. 

Contractor Overview

Multiple contractors were needed to complete this project. A licensed general contractor was hired for the flooring, kitchen, bathroom, painting, windows and all carpentry. A licensed plumber was hired for all new plumbing and heating. A licensed electrician was hired for all electrical work. And professional insect exterminator was hired for yellow jacket removal.

Exterior

  1. Power wash exterior of building
  2. Rework existing enclosed front entrance – convert to open front stoop
    • Demo what is need, rebuild as necessary
  3. Repair all exterior doors as needed, replace all hardware
  4. Install new house numbers, mailboxes and doorbells
  5. Replace all windows (new vinyl double hung)
  6. Paint all trim on bottom of windows – Color – Spinach #20-20
  7. Repair rear stairs/decks as needed and paint (grey exterior paint)
  8. Remove all trash from yard
  9. Install white picket fence along front yard (pre made sections)
  10. Clean front yard and mulch flower bed

Roof

  1. Inspect entire roof and patch were needed
Search for listings now!

Interior — General

  1.  Paint scheme:  Navajo eggshell walls, semi gloss white trim and doors, flat white ceilings and closets
    • Purchase all paint thru Eddie Pocoski from Pratt & Lambert
    Color Name Product Code
    Navajo Eggshell Gold Eggshell Navajo Wall Z8291
    Ceiling White Gold Flat Super 1-Coat White Z8100
    Trim White Gold Semi-Gloss Super 1-Coat White Z8300
  2. Patch were needed paint all rooms in house with above color scheme
  3. Repair all stairs as needed, front and rear and paint railings and spindles
  4. Remove all old carpeting
  5. Repair all interior doors as needed (all doors must open and close properly and lock)
  6. Install new vinyl double hung windows
  7. Remove all trash and debris from all floors, including basement

First (1st) Floor Apartment

  1. Replace all windows w/ vinyl double hung
  2. Prep and paint all rooms (see above color scheme)
  3. Finish framing in 3rd bedroom and closet in front room (as per attached diagram)
  4. Carpet living room (color – Wet Sand)
  5. Carpet in all bedrooms (color – Wet Sand)
Before and After - Shultas
First Floor — Before
Before and After - Shultas
First Floor — After

Kitchens

  1. Patch and repair all walls and paint as per above color scheme
  2. Replace cabinets – Star Oak
    • Star Oak Sink Base 60" (3) at $214.40/ea
    • Star Oak Wall Cabinet 60"x30" w/ open shelf (3) @ $200.40/ea
    • Star Oak Wall Cabinets 18"30 (3) at $75.74/ea
  3. Install new dark laminate countertop w/7" sink, with single handle faucet
    • Labrador Granite Formica Counter (3) at $100.00/ea
  4. Install new white appliances (Frig., electric stove and hood)
    • Electric Stove (3) – Whirlpool, Lowes item #235957, $298/ea
    • Refrigerator (3) – Whirlpool, Lowes item #155723, $398/ea
  5. New flooring (sheet vinyl – Armstrong Initiator #66087)
  6. Replace light fixtures as needed
  7. New sink and faucet
Before and After - Shultas
Kitchen 1 — Before
Before and After - Shultas
Kitchen 1 — After
Before and After - Shultas
Kitchen 2 — Before
Before and After - Shultas
Kitchen 2 — After

Bathrooms

  1. Paint according to scheme
  2. Install new GFI outlet
  3. Install new 3 piece tub surround
  4. Install new diverter and shower head
  5. Install new toilet
  6. Replace sink base, top and faucet. Install new medicine cabinet
  7. Install new flooring (sheet vinyl – Armstrong Initiator #66087)
Before and After - Shultas
Bathroom — Before
Before and After - Shultas
Bathroom — After
Before and After

Bedrooms

  1. Prep and paint according to house color scheme
  2. Repair doors as needed
  3. Replace all light fixtures
  4. Carpet all floors (Color – Wet Sand)

2nd floor apartment

  1. Same as 1st floor apartment

3rd floor apartment

  1. Same as 1st floor apartment

Plumbing and Heating

  1. Install (3) new gas fired boilers
  2. Install (3) new hot water heaters – electric
  3. Install new radiation baseboards on all floors, conduct heat lose and supply
  4. Replace all missing drainage and supply lines for all floors
  5. Replace 3 tub diverters and inspect all plumbing
  6. Install washing machine hook up in basement
  7. Replace all bathroom fixtures – sink, toilet and tub
  8. Install (3) new kitchen faucets and sinks
Before and After - Shultas
Heating — Before
Before and After - Shultas
Heating — After

Electrical

  1. Replace light fixtures in all rooms were needed (Pull chain with 2 bulbs)
  2. Complete installation of new service as needed
  3. Repair service into house as needed
  4. Label panel box as well
  5. Install Romex were needed
  6. Install new smoke and co detectors to code – Battery Powered
  7. Install all new switches were needed
  8. Repair outlets to code
  9. Install GFCI to code in all 3 floors
  10. Replace thermostats on all floors (use inexpensive models)
  11. Install dryer plugs and washer outlet in basement
  12. Install new plugs for stove and make sure they are wired correctly
  13. Work with plumber to wire new boilers
  14. Coordinate final inspections
Search for listings now!

Basement

  1. Remove all trash and debris
  2. Remove unused wires, pipes, etc as needed
  3. Repair all doors including hatch door and rebuild stairs
  4. Inspect all wood, replace as needed
  5. Spray entire basement – white walls
  6. Repair lighting as needed
  7. Replace basement hoppers and paint frames
  8. Repair stairs as needed and paint

Landscaping

  1. Remove all trash and debris
  2. Remove unused wires, pipes, etc as needed
  3. Repair all doors including hatch door and rebuild stairs
  4. Inspect all wood, replace as needed
  5. Spray entire basement – white walls
  6. Repair lighting as needed
  7. Replace basement hoppers and paint frames
  8. Repair stairs as needed and paint

FINAL COST BREAKDOWN

  1. General Contracting – $39,000.00
    • All framing – material and labor
    • Sheetrock, Interior and Exterior Painting
    • Window Replacement
    • Kitchen cabinets, countertop and appliances
    • All Flooring – carpet and vinyl
    • All finish work – coordinate all inspections
  2. Electrical – $9,000.00
    • Complete wiring of entire house to code
    • Add new smoke & CO detectors to code
    • Inspect all existing wiring and replace all outlets and switches
    • All fixtures – coordinate all inspections
  3. Plumbing – $9,000.00
    • All new rough plumbing, fixtures and finish work
    • 3 kitchens and 3 bathrooms
    • Coordinate all inspections
  4. Heating – $9,000.00
    • 3 new gas fired boilers with new baseboards on all floors
    • Coordinate all inspection
  5. Permits – $2,000.00

Total Repair Cost = $68,000.00

Before and After